Line D is the fourth line of the Prague Metro. Section I.D is to run from Náměstí Míru via Pankrác and Krč to Depo Písnice at the southern edge of the city and to have ten stations.[3] The whole route is 10.6 kilometres long and is to be the first in Prague to operate automatically without a driver.[11][15] The investor in the construction is the Prague Public Transit Company (DPP), and the designer is the company Metroprojekt.[1]
The 1970s: a branch of Line C was to serve the south
The first plans for Line D arose in the 1970s.[11] The concept of the time, last prepared in 1983, assumed a different alignment of route D, roughly along the right-bank tram line to the area of Palackého náměstí. The southern sector of the city was to be served by a branch of Line C diverging at Pankrác station.[1] On the southern side of Pankrác C station, a spur was built in the 1970s, which was intended for connecting the future route D.[6] According to Metroprojekt, housing estate construction in the south of Prague exceeded the original assumptions, and it was therefore decided that the branch of Line C would be a separate route D continuing to the north. The right-bank area of the southern part of the city was left to trams.[1]
1991–2001: Zálesí, Kačerov or Pankrác
In 1991, Metroprojekt prepared the construction brief for I.D in the extent Zálesí–Náměstí Míru, later extended by the Nové Dvory station.[1] In 1992 it examined a variant with a crossing with Line C at Kačerov station. Of the examined interchange locations to Line A, Náměstí Míru was confirmed.[1]
In 1993, Metroprojekt compared, for the Nové Dvory–Hlavní nádraží section, an automatic rubber-tyred metro of the VAL type with a light rail tram, in corridor "P" via Pankrác as well as in corridor "K" via Kačerov. After assessment, the solution with the Pankrác interchange station, on which the zoning plan is based, was confirmed.[1]
After 1993, preparation of Line D stagnated, because the northern extension of Line C was given priority. In 2001, Metroprojekt re-examined the Nové Dvory–Náměstí Míru section as a basis for a building closure. Instead of the Zálesí station, it proposed a Nemocnice Krč station by the Thomayer Hospital.[1]
2006–2012: light metro or automatic metro in the standard profile
A comparative study from 2006 assessed a light automatic rubber-tyred metro as the most advantageous. The Prague City Council then stated in its programme statement for 2006–2010 that the parameters of a light metro should be preferred for route D.[1]
In 2010–2011, Metroprojekt prepared documentation for the zoning decision and EIA documentation for the Depo Písnice–Náměstí Míru section. The design assumed automatic operation without a driver, the CBTC signalling system and platform screen doors, but the dimensions of the tunnels and platforms remained the same as on Lines A, B and C.[1] The EIA opinion was issued on 2 November 2012.[2] By resolution no. 2241 of 18 December 2012, the Prague City Council announced the intention to build the first stage Pankrác–Depo Písnice in a system compatible with the existing lines.[1]
2013–2015: the intention, the zoning decision and trains without drivers
On 8 October 2013, the Council of the Capital City of Prague approved the intention to build route I.D and the inclusion of the project in the Operational Programme Transport 2014+.[1] According to plans at the time, the route was to be finished by 2022. The then mayor Tomáš Hudeček (TOP 09) said that the section from Náměstí Míru to Písnice would cost 60 billion crowns.[11]
In 2014 it was decided that the first section would also include the Pankrác D station and that Line D would be operationally independent. The zoning decision for the whole route Náměstí Míru–Depo Písnice became final after several appeals in July 2014.[1] By resolution no. 1685 of 21 July 2015, the Prague City Council decided on driverless operation.[2] On 22 July 2015, the Municipal Court in Prague annulled the zoning plan change Z 2440/00, which specified the route corridor in the Pankrác–Depo Písnice section.[2]
2016–2019: land, phasing and geological survey
In June 2016, DPP applied for a building permit for the Pankrác–Depo Písnice section without the train depot.[2] By a resolution of the city assembly of 23 February 2017, the Capital City decided on a new procurement of the annulled zoning plan change.[2] A phasing study from 2017 recommended starting construction at Pankrác, where the station needs the longest construction time.[1]
In March 2018, the transport committee of Prague City Hall discussed an estimate of 39.7 billion crowns for the Pankrác–Depo Písnice section. DPP's director general Martin Gillar said at the time that the company needed to reach agreement with the owners of 451 of the 655 plots required.[21] Owners of plots by the Arkády Pankrác shopping centre withdrew their lawsuit against the zoning decision on 13 March 2019, and owners of plots by the Nádraží Krč and Nemocnice Krč stations on 5 August 2019.[2] In 2019, Metroprojekt proposed the so-called Variant VI, which divided the Pankrác–Depo Písnice section into three phases: Pankrác–Olbrachtova, Olbrachtova–Nové Dvory with tunnelling by TBM machines from Písnice, and finally the Libuš and Písnice stations and Depo Písnice with the depot.[1]
In May 2019, the council and assembly of the capital approved a supplementary geological survey. Its ceremonial start took place on 19 June 2019, and according to DPP the city leadership presented it as the start of construction of the whole route.[1] The chronology of the Prague Metro on the DPP website also gives this date as the start of construction of Line D.[4] The amendment to the Railways Act enabling automatic metro operation has been in force since 13 December 2019.[2] DPP submitted the application for a new building permit for Variant VI on 30 December 2019.[2]
2020–2022: objections, bias and the building permit
A schedule from early 2020 assumed the start of construction on 1 July 2020 and commissioning of the line on 31 December 2027.[5] The tender for the first section was challenged at the Office for the Protection of Competition (ÚOHS) by the company Eurovia. The ÚOHS chairman rejected its appeal on 28 June 2021.[2] According to Seznam Zprávy, Eurovia also complained to the European Commission that the contract was tailored for a competitor.[23] On 29 June 2021, DPP signed the contract for the Pankrác–Olbrachtova section with a consortium of Subterra, HOCHTIEF CZ, STRABAG, HOCHTIEF Infrastructure and Ed. Züblin at a bid price of 13.75 billion crowns.[1]
On 12 May 2020, an objection of bias against all official persons of City Hall, including the director, and in the tree-felling proceedings also the mayor, was filed in the proceedings. Neither the Ministry of the Environment nor the Ministry of Transport upheld it.[2] The assembly approved the zoning plan change 2440/00 again on 22 April 2021. The building permit for the Pankrác–Nové Dvory section was issued on 30 June 2021 and became final on 24 March 2022. The Municipal Court in Prague dismissed the lawsuit of the Pankrác Society (Pankrácká společnost) and residents of Kovařovicova Street on 8 February 2023, and the Supreme Administrative Court of the Czech Republic dismissed the cassation complaint on 2 August 2023.[2]
Construction of the first section I.D1a Pankrác–Olbrachtova officially began on 21 April 2022. DPP assumed 90 months of construction and commissioning of the whole line at the end of 2029.[6] According to the then mayor Zdeněk Hřib (Pirates), it was the first start of construction of a new Prague Metro line in more than 40 years.[6]
Olbrachtova–Nové Dvory: from the winner in September 2023 to the contract in April 2026
DPP announced the contract for the second section I.D1b on 30 May 2022 with an estimated price of 24.63 billion crowns.[1] Construction was to begin in October 2023.[5] DPP describes the course of the tender as follows:[2]
- On 5 September 2023, DPP excluded the consortium led by the company PORR and chose the consortium led by Subterra as the winner.[2]
- On 15 January 2024, ÚOHS at first instance annulled the selection of the contractor, and on 13 March 2024 the DPP board also annulled the selection.[2]
- On 6 August 2024, DPP chose the same contractor for the second time; ÚOHS annulled its selection on 28 January 2025, and on 9 April 2025 the office's chairman discontinued the proceedings, annulling the selection notice.[2]
- On 22 September 2025, the ÚOHS chairman confirmed the exclusion of the group of PORR, Vinci and Marti, and on 29 September 2025 DPP chose Subterra for the third time.[2]
- On 8 October 2025, the Regional Court in Brno prohibited the conclusion of the contract, on 10 February 2026 ÚOHS rejected the objections of the company Strabag, and on 27 February 2026 the Supreme Administrative Court of the Czech Republic annulled the interim measure.[2]
- On 7 April 2026, DPP signed the contract with a consortium of Subterra, HOCHTIEF CZ, HOCHTIEF Infrastructure and BeMo Tunneling for 29.99 billion crowns excluding VAT.[2]
Deputy Mayor for transport Jaromír Beránek said in April 2026 that Prague had lost 2.5 years because of the dispute among the contractor consortia. He estimated the social cost of each year without Line D at roughly ten billion crowns in today's prices.[16] The chairman of the DPP supervisory board, Zdeněk Hřib (Pirates), said at the start of construction on 19 June 2026 that the unsuccessful bidder had used "all possible and impossible routes". The opposition councillor Adam Scheinherr (Praha Sobě) said on the same day that he had handed the tender over to the current coalition prepared and that completing it had taken the whole electoral term.[13]
Ten stations and three operating sections
Section I.D1 Pankrác–Nové Dvory has an operating length of 4.6 kilometres, the adjoining section I.D2 to Depo Písnice 3.8 kilometres, and section I.D3 from Pankrác to Náměstí Míru 2.7 kilometres.[3] Until the Písnice depot is finished, trains are to depart from the Kačerov depot along a 468-metre connection between Lines C and D.[6] The stations from the north:
- Náměstí Míru: a mined single-vault station above the existing Line A station in Prague 2, prepared for continuation to the centre.[3]
- Nusle (working name Náměstí Bratří Synků): a cut-and-cover station with an island platform.[3][14]
- Pankrác: a single-vault interchange station with side platforms, track level 33 metres below the surface, the largest station of the line.[6]
- Ryšánka (working name Olbrachtova): the first mined twin-vault station of the Prague Metro, with platforms in a curve.[6]
- Nádraží Krč: the only surface station of the line, with platforms on a bridge over the Kunratický potok valley and with the control centre of the whole route D.[15]
- Nemocnice Krč: a cut-and-cover station by the Thomayer Hospital, track level 17 metres below ground.[15]
- Nové Dvory: a mined single-vault station with a platform 33 metres below ground and with a branching for a future spur to Modřany.[15]
- Libuš: a cut-and-cover station along Novodvorská Street, rail head about 13 metres below ground.[9]
- Písnice: a cut-and-cover station with a bus terminal and a park-and-ride car park for 396 cars.[3]
- Depo Písnice: a cut-and-cover terminal station with a train depot and a park-and-ride car park for 873 cars.[3]
On 31 August 2026, the Prague City Council approved the names Nusle and Ryšánka. It did not approve the proposals Tempo for Nové Dvory, Sídliště Písnice for Písnice and Prameny for Depo Písnice.[14] The dispute over the name Olbrachtova began with criticism that the writer Ivan Olbracht was a communist. Renaming was recommended by Zdeněk Hřib, and the director of the Institute for the Study of Totalitarian Regimes, Ladislav Kudrna, spoke similarly.[16][14]
From 60 to 120 billion: price estimates
The estimates differ in the extent of the section and the price level:
- Mayor Tomáš Hudeček (TOP 09) gave 60 billion crowns for the Náměstí Míru–Písnice section.[11]
- 13 March 2018: a document for the City Hall transport committee gave 39.7 billion for the Pankrác–Depo Písnice section, of which 21 billion for tunnels and vestibules, 6.5 billion for trains and the control system and 5.7 billion for depots and car parks.[21]
- 21 March 2019: Deputy Mayor Adam Scheinherr told the city assembly 72 billion for the Písnice–Náměstí Míru route, of which according to Metroprojekt 57 billion for the Depo Písnice–Pankrác section. The opposition councillor Petr Stuchlík (ANO) criticised the increase.[22]
- June 2021: a presentation by DPP director Petr Witowski to councillors gave 97.8 billion against 72.6 billion calculated two years earlier. According to it, each year of delay costs two to four billion in inflation.[23]
- July 2021: according to Pražský deník, the estimate for the Pankrác–Nové Dvory section with five stations was 52 billion crowns.[25]
- 21 April 2022: DPP gave 97.79 billion for the whole route I.D and 14.54 billion for the Pankrác–Olbrachtova section including monitoring.[6]
- June 2025: the daily E15 wrote that the latest estimate was 120 billion crowns.[24]
In addition there are the contracts awarded and announced: 13.75 billion for construction of the Pankrác–Olbrachtova section[1], 29.99 billion excluding VAT for the Olbrachtova–Nové Dvory section[2] and an estimated 3.755 billion excluding VAT for the Libuš station.[9] The tender for automatic trains and the transport system for Lines C and D has an estimated value of roughly 86 billion crowns excluding VAT.[20]
A loan of 22.76 billion from the European Investment Bank
In 2014 the city negotiated co-financing from European Union funds, and the construction was entered among the major projects of the Operational Programme Transport 2014+.[1] In June 2022, Prague councillors approved a loan from the European Investment Bank equivalent to roughly 22.76 billion crowns, which is to cover about half of the costs.[12] Minister for Regional Development Klára Dostálová (ANO) promised in July 2021 that the state would contribute to Line D and the city ring road in Prague, but did not state a specific amount.[25]
Status as of 2 October 2026
On the first section, according to a DPP overview, all tunnelling work in the Pankrác–Ryšánka route section had been completed as of 25 September 2026. For October and November 2026, concreting of the vault is planned at Pankrác D station, and concreting of the secondary lining and work on the vestibules at Ryšánka station.[10] The Olbrachtova station was excavated in October 2025 after 19 months of tunnelling.[19] The reconstructed Pankrác C station opened on 19 December 2025.[1]
Construction of the Olbrachtova–Nové Dvory section officially began on 19 June 2026. It is to last 72 months and run from 13 construction site facilities.[7] On 18 September 2026, tunnelling began on an access and ventilation tunnel of the Nové Dvory station about 300 metres long, which is to last until the end of the first quarter of 2027.[8]
The office DESU issued a permit for the Nové Dvory–Libuš section on 20 September 2026, and it is expected to become final in October 2026.[2] On 2 October 2026, DPP announced the tender for the Libuš station with a construction time of 54 months. Deputy Mayor Beránek said that the station could open together with the first section in 2032.[9] The EIA opinion is valid until 31 December 2026. Under an amendment signed on 17 September 2026, it can be extended also for the metro, and DPP will apply for this by the end of the year.[2]
For the Pankrác–Náměstí Míru section, DPP expects to announce tenders in April 2027.[2] According to a schedule cited by the website Zdopravy.cz in February 2026, construction is to begin in spring 2029, last 84 months and end in 2036.[18] DPP also commissioned a feasibility study of a 2.2-kilometre extension from Náměstí Míru via Hlavní nádraží to Náměstí Republiky, with construction assumed in 2037–2044.[18] In the tender for automatic trains, Alstom and the consortium of Siemens Mobility and Škoda Transportation are continuing in the negotiation phase. So far 69 trainsets have been assumed, of which 16 for Line D.[20]
Six opening dates
- October 2013: the route from Pankrác to Písnice was to be finished by 2022.[11]
- Early 2020: commissioning on 31 December 2027.[5]
- 21 April 2022: commissioning of the whole route at the end of 2029.[6]
- 7 April 2026: according to Zdopravy.cz, "the year 2031 is being discussed" for the section from Pankrác to Písnice.[17]
- 9 April 2026: Deputy Mayor Beránek gave the opening of the first part at approximately mid-2032 and arrival at Depo Písnice in the optimistic case in 2034–2035.[16]
- 19 June 2026: DPP assumes commissioning of the Pankrác–Nové Dvory section in the second half of 2032.[7]
Chronology
- 1983: last documentation of the concept with a branch of Line C to the south.[1]
- 18 December 2012: the city council chooses a system compatible with Lines A, B and C.[1]
- 8 October 2013: the city council approves the intention to build route I.D.[1]
- July 2014: zoning decision Náměstí Míru–Depo Písnice final.[1]
- 21 July 2015: the city council decides on driverless operation.[2]
- 19 June 2019: ceremonial start of the geological survey.[1]
- 29 June 2021: contract for the Pankrác–Olbrachtova section for 13.75 billion.[1]
- 21 April 2022: start of construction of the Pankrác–Olbrachtova section.[6]
- June 2022: the city assembly approves a loan from the European Investment Bank.[12]
- 7 April 2026: contract for the Olbrachtova–Nové Dvory section for 29.99 billion excluding VAT.[2]
- 19 June 2026: start of construction of the Olbrachtova–Nové Dvory section.[7]
- 31 August 2026: the city council approves the names Nusle and Ryšánka.[14]
- 18 September 2026: start of tunnelling at Nové Dvory.[8]
- 2 October 2026: tender for the Libuš station.[9]
Summary as of 2 October 2026
Two sections with five of the ten stations are under construction: Pankrác–Ryšánka since April 2022 and Ryšánka–Nové Dvory since June 2026.[7] DPP states commissioning of the Pankrác–Nové Dvory section in the second half of 2032.[7] In April 2022, by contrast, it assumed opening of the whole route at the end of 2029.[6] The contract prices of the two sections under construction are 13.75 billion and 29.99 billion excluding VAT.[1][2] The latest published estimate for the whole route is 120 billion crowns; in 2022 DPP gave 97.79 billion.[24][6] A tender has been announced for the Libuš station since 2 October 2026.[9] The Písnice and Depo Písnice stations and the Pankrác–Náměstí Míru section do not yet have a contractor.[7][2]
Sources
- Dopravní podnik hl. m. Prahy
- Dopravní podnik hl. m. Prahy
- Dopravní podnik hl. m. Prahy
- Dopravní podnik hl. m. Prahy
- Dopravní podnik hl. m. Prahy
- Dopravní podnik hl. m. Prahy — 21 April 2022
- Dopravní podnik hl. m. Prahy — 19 June 2026
- Dopravní podnik hl. m. Prahy — 18 September 2026
- Dopravní podnik hl. m. Prahy — 2 October 2026
- Dopravní podnik hl. m. Prahy — 25 September 2026
- ČT24 (Česká televize) — 21 April 2022
- ČeskéNoviny.cz (ČTK) — 17 June 2022
- ČeskéNoviny.cz (ČTK) — 19 June 2026
- ČeskéNoviny.cz (ČTK) — 31 August 2026
- Zdopravy.cz — 19 June 2026
- Zdopravy.cz — 9 April 2026
- Zdopravy.cz — 7 April 2026
- Zdopravy.cz — 16 February 2026
- Zdopravy.cz — 30 October 2025
- Zdopravy.cz — 19 May 2026
- Pražský deník — 13 March 2018
- E15 — 21 March 2019
- Seznam Zprávy — 17 June 2021
- E15 — 27 June 2025
- Pražský deník — 20 July 2021