Ředitelství silnic a dálnic (ŘSD) is a state organisation that manages and builds motorways and first-class roads in the Czech Republic. The organisation is headed by Director General Radek Mátl.[1][2]
Construction of the D11 motorway
ŘSD is the investor in the completion of the D11 motorway, which runs from Prague through Hradec Králové to the Czech-Polish border at Královec in the Trutnov area. Construction of D11 began in 1978; of the planned 154 kilometres, 113 kilometres are finished, and since December 2021 the motorway has ended at the northern edge of Jaroměř.[1]
The 19.6-kilometre section of D11 between Jaroměř and Trutnov has been under construction since April 2026 by a consortium of the companies EUROVIA CZ, MI Roads, Metrostav TBR and M-Silnice, at a price of CZK 9.09 billion excluding VAT. According to ŘSD, the section is to be finished in autumn 2029.[1][2]
On 3 November 2026, tunnelling of the Kamenný vrch tunnel between Kocbeře and Výšinka began on this section. The tunnel will have two tubes 780 and 756 metres long, and the mined part of each tube is to be 684 metres. According to representatives of the construction companies and ŘSD, tunnelling is to take roughly a year.[1][3] Mátl said that the construction season had been used well and that builders had excavated 53,000 cubic metres of soil at the tunnel's construction pit.[1]
On the adjoining section of D11 between Trutnov and the state border at Královec, whose construction began in October 2024, ŘSD is building the Poříčí and Opevnění tunnels. According to ČTK and iDNES.cz this section is 17.9 kilometres long and costs CZK 11.7 billion excluding VAT; according to Ekonomický deník its length is 21 kilometres.[1][3][2] According to ŘSD, the whole section should be finished in the second half of 2028, and ŘSD plans to open a three-kilometre part near the Polish border on 27 November 2026.[2]
Further plans
ŘSD has obtained a positive environmental impact assessment opinion for widening D11 to six lanes between Prague and Poděbrady. According to Ekonomický deník, long-term delays and disputes accompany the completion of D11.[2]
Chronology
- — Construction began near Nový Jičín on the last section of the D48 motorway; completion is planned in about three years. → Zdopravy.cz Novinky.cz
- — The Pisárecký tunnel and the Hlinky tunnel in Brno are to be closed from 12 October to 20 November 2026 for repairs planned by the Road and Motorway Directorate (Ředitelství silnic a dálnic). → Deník: Jihomoravský kraj Brněnská Drbna
- — From 3 October 2026, the exit ramp from the D2 motorway from Bratislava to the D1 towards Ostrava is closed in Brno until 28 November, while traffic is being moved to a new ramp from the D1 from Prague to the D2. → Deník: Jihomoravský kraj Zdopravy.cz
- — The Ministry of Transport extended the trial operation of the increased speed limit of 150 km/h on a section of the D3 motorway between the Tábor area and České Budějovice until the end of 2026. → Novinky.cz Budějcká Drbna
- — The Liberec Tunnel on road I/35 will be gradually closed tube by tube from 9 to 12 October 2026 for routine maintenance, with traffic reduced to a 1+1 regime. → Deník: Liberecký kraj Liberecká Drbna
- — The Road and Motorway Directorate is repairing the D5 motorway in the Plzeň Region between kilometres 88 and 94, from Líně to Nýřany; the first part of the work will last until the end of November, the second from spring to summer. Deník: Plzeňský kraj Plzeňská Drbna
- — The bridge over road I/35 in Hodkovice nad Mohelkou in the Liberec area, replaced after demolition by a new structure costing 72 million crowns excluding VAT, is to reopen on Thursday 15 October 2026 after half a year of restrictions. → Deník: Liberecký kraj Liberecká Drbna
- — The Road and Motorway Directorate started replacing the bearings of two bridges on the D1 motorway in the Vysočina Region while keeping traffic running, with work worth over 17 million koruna to last until mid-December. → Jihlavská Drbna iROZHLAS
- — Repairs to half of the bridge on the I/35 through-route in Liberec towards Děčín have been completed, and from Sunday, 1 November, traffic will run without restrictions. → Deník: Liberecký kraj Liberecká Drbna
- — The start of construction on the final missing section of the D55 motorway between Olomouc and Přerov has been postponed from this year to 2027 due to an objection from one of the unsuccessful bidders for the contract. → Deník: Olomoucký kraj Zdopravy.cz
- — Excavation began on the Kamenný vrch tunnel on the D11 motorway between Jaroměř and Trutnov, with a mined section 684 metres long; the excavation is to take about a year and the whole section is to be finished in autumn 2029. → ČTK / České noviny Ekonomický deník
- — The longest bridge on the new section of the D35 motorway between Sadová and Plotiště near Hradec Králové successfully passed a load test with a total weight of 48 tonnes. → Deník: Královéhradecký kraj Hradecká Drbna
- — The section of the D55 motorway between Napajedla and Babice in the Zlín Region has received a building permit, with main construction expected to start in spring 2027 and completion planned for 2030. → Deník: Zlínský kraj iROZHLAS
- — The Ředitelství silnic a dálnic announced that it will open the new overpasses above the Prague Ring Road in December 2026, later than originally planned, because drilling for the relocation of a high-voltage line hit hard rock. → Pražský deník iDNES.cz, Praha
- — The Ředitelství silnic a dálnic opened a bypass of the village of Svor on road I/9, costing more than half a billion crowns, diverting transit traffic away from the built-up part of the village. → Liberecká Drbna iDNES.cz: Liberec
- — Ředitelství silnic a dálnic will open the repaired section of road I/35 in Liberec between České mládeže and Hodkovická streets on Saturday, 14 November, a week earlier than planned. Deník: Liberecký kraj Liberecká Drbna
- — The regional office suspended the permitting procedure for the Šternberk bypass after protected butterfly species were found along its planned route, delaying the construction by at least two years. Hanácká Drbna Deník: Olomoucký kraj
- — Along the Svratka river in Brno, the cycle path will be closed from 17 November to 31 March due to the ongoing reconstruction of the D1 and D2 motorway interchange. → Deník: Jihomoravský kraj Zdopravy.cz
- — A new six-kilometre section of the D3 motorway between Kaplice and Nažidla in the South Bohemian Region will open on 26 November, replacing the existing I/3 road. → iDNES.cz, Praha Lidovky.cz