Ředitelství silnic a dálnic announced that it will open the new overpasses over the Prague Ring Road in December 2026, later than it had originally expected.[1][2] The reason is a longer preparation of the construction because of difficult ground conditions.[1][2]

The original plan and the delay

Work on building the new overpasses began in mid-May. The overpass in the street K Austisu was originally due to open on 15 October and the second on 14 December.[1][2] The demolition of the old bridges was postponed by a month. Before it, a high-voltage line had to be relocated, but when drilling an underground tunnel for the new cables the machinery hit hard rock.[1][2]

Luděk Hubáček of Ředitelství silnic a dálnic described how the method of work had to be changed and a heavy drilling rig for rock massifs brought in. Drilling, he said, was complicated by groundwater and by drilling mixture that began seeping through fissures in the rock onto the carriageway of the D0 motorway. The cables had to be safe before demolition machinery was deployed, and the follow-up works were therefore also pushed back.[1][2]

Costs

The construction is carried out by the company Skanska. The costs of the projects were originally estimated at 207 million crowns excluding VAT. According to Hubáček, they will rise because of the more demanding drilling and adjustments to construction procedures; the amount of the additional costs is the subject of contractual negotiation and approval in a change-order procedure.[1][2]

Widening of the D0 section

The new overpasses are connected with the planned widening of the D0 section between Třebonice and Slivenec by a third lane in each direction. According to an information leaflet of Ředitelství silnic a dálnic, construction is to start in 2027 and end in 2029. It is the oldest section of the Prague Ring Road, opened in 1983, and one of the busiest; up to 75,100 vehicles pass along it every day.[1][2]

Chronology

  • — The Ředitelství silnic a dálnic announced that it will open the new overpasses above the Prague Ring Road in December 2026, later than originally planned, because drilling for the relocation of a high-voltage line hit hard rock. Pražský deník iDNES.cz, Praha