The Kamenný vrch Tunnel on the D11 motorway between Jaroměř and Trutnov will have two tubes 780 and 756 metres long and will be the longest tunnel on the whole motorway.

The Kamenný vrch Tunnel is being built on the Jaroměř–Trutnov section of the D11 motorway, between Kocbeře and Výšinka in the Trutnov area. It is the key structure of the section and, once completed, will be the longest tunnel on the D11 [1][2].

Parameters

The tunnel has two tubes: the left one is 780 metres long, the right one 756 metres. The mined part of both tubes measures 684 metres and is followed by cut-and-cover portal sections. Two cross-passages for the escape of people connect the tubes, and the tunnel will allow traffic to be switched to the opposite carriageway during maintenance of one of them [1][2][3].

Construction

The 19.6-kilometre D11 section from Jaroměř to Trutnov costs CZK 9.09 billion excluding VAT. Construction began in April 2026 and is to be completed in autumn 2029. The section is being built by a consortium of the companies EUROVIA CZ, MI Roads, Metrostav TBR and M-Silnice; the tunnel is the responsibility of Metrostav TBR and Marti CZ [1][2].

Mining began on 3 November 2026 and, according to representatives of the builders and of Ředitelství silnic a dálnic, is to take about a year. The New Austrian Tunnelling Method with explosives is used, and work is to continue around the clock; about 70 people are to work on the tunnel. At the start, in keeping with tradition, the builders placed a statue of Saint Barbara on the wall of the northern portal, blessed by a priest from Trutnov. The Director General of ŘSD, Radek Mátl, said that 53,000 cubic metres of soil had been excavated at the tunnel's construction pit [1][3].

Context

The D11 from Prague via Hradec Králové to the Czech–Polish border at Královec has been under construction since 1978. Of the planned 154 kilometres, 113 are complete according to reports; since December 2021 the motorway has ended at the northern edge of Jaroměř. On the section from Trutnov to the border, the Poříčí and Opevnění tunnels are being built, which will be shorter than Kamenný vrch [1][3].

Chronology

  • — Mining of the Kamenný vrch Tunnel, with a mined part 684 metres long, began on the D11 motorway between Jaroměř and Trutnov; mining is to take about a year and the whole section is to be finished in autumn 2029. → ČTK / České noviny Ekonomický deník

Sources

  1. U Výšinky na Trutnovsku začala na D11 ražba tunelu Kamenný vrch · ČTK / České noviny · 3 November 2026
  2. Obrazem: D11 se blíží k polským hranicím. Začala ražba nejtěžší části · Ekonomický deník · 3 November 2026
  3. Na Trutnovsku začala ražba tunelu Kamenný vrch, bude nejdelším na D11 · iDNES.cz: Hradec Králové · 3 November 2026