Hradčanská is a station on line A of the Prague metro in Prague 6. It opened in 1978 and has not undergone a complete reconstruction since. The most critical places were rehabilitated and the escalators replaced in 1996 [1][2].

According to Daniel Veverka, head of the Metro Investment department at the Prague Public Transit Company (DPP), the station's technology and interior fittings are at the end of their service life, including those replaced thirty years ago [1]. DPP has therefore begun preparatory work for a complete modernisation of the station. It is carried out with the station in full operation until about the middle of January 2027, in local work zones on all levels. According to Lukáš Radil, director of civil engineering operations at Metrostav CZ, workers can only work between midnight and three in the morning [1][2][3].

The contractor for the modernisation is a consortium of Metrostav CZ and Geosan Group, and the cost is CZK 1.134 billion excluding VAT [1][2][3]. In the preliminary works, the cladding of the pillars, the central nave of the platform and the walls behind the tracks is being removed, ceiling panels are being taken down in the concourse, unneeded cables are being removed throughout the station, and temporary electrical distribution is being built [1][2].

From Saturday 16 January 2027 the station is to be closed completely, including the concourse and the underpass. Trains are to pass through at reduced speed, and DPP expects the station to reopen at the end of 2027. In the Prague 6 area, tram lines will be strengthened, and passengers can also use trains from Praha-Dejvice station [1][2]. According to Zdopravy.cz, the closure was originally planned for summer 2026 and was postponed because of the reconstruction of Flora station, so that two stations on line A would not be closed at the same time [1].

After the closure, the contractors will strip the station, uninstall the three-armed escalators together with the machine room, and remove the original load-bearing reinforced-concrete structures, the side technical staircases and the ageing intermediate ceiling in the escalator tunnel. They will carry out rehabilitation of leaks and lining on all levels, reconstruct the drainage, build new cable trays and replace the cable and ventilation distribution. The lighting will also be new. The aluminium cladding cassettes will be refurbished, the stone cladding and paving will be cleaned and damaged parts replaced with new ones. Four retail units and the public toilets in the underpass are also to be renewed [1][2].

The current modernisation does not include building a lift, so the station will not be barrier-free after reopening. Prague 6 criticised this in the past [1]. DPP said it is preparing step-free access as a separate investment project, coordinated with Správa železnic and with the modernisation of the Praha – Kladno railway line. The aim is to link the metro station with the railway station by lifts [1][2]. Deputy Mayor of Prague for transport Jaromír Beránek (Czech Pirate Party) said that the modernisation will create the technical basis for a future step-free connection to the new railway station [3].

Sources

  1. O datu uzavření metra Hradčanská je rozhodnuto. Vytíženou stanici nahradí na téměř rok tramvaje či vlaky · Zdopravy.cz · 2 November 2026
  2. Stanice metra Hradčanská by se měla kvůli opravě uzavřít 16. ledna · ČTK / České noviny · 2 November 2026
  3. Stanice metra Hradčanská se od poloviny ledna na rok uzavře · Novinky.cz · 2 November 2026