Firesta-Fišer, rekonstrukce, stavby is a construction company and a member of a consortium together with OHLA ŽS, Valcano and Duna Aszfalt.[1] In mid-September 2026 the group won a tender run by the Ředitelství silnic a dálnic (ŘSD) to complete the last missing section of the D55 motorway between Olomouc and Přerov.[1][2]
The D55 contract
The group including Firesta-Fišer submitted a bid of 1.641 billion crowns excluding VAT for the Kokory – Přerov section, the lowest of five bids received.[2] The estimated value of the contract was 2.454 billion crowns.[2] The section is almost six kilometres long and is to include seven bridges, a footbridge for pedestrians and cyclists, and two noise barriers.[1][2]
Delay of construction start
One of the unsuccessful bidders filed an objection against the result of the tender.[1][2] Miroslav Mazal, spokesperson for the Olomouc branch of the ŘSD, confirmed this and said that "we will therefore specify the date for the start of construction".[1] Until the objection is resolved, the ŘSD cannot sign a contract with the group to begin work, and the dispute may also end up before the Úřad pro ochranu hospodářské soutěže.[2]
The updated ŘSD schedule, which had assumed that construction would start as early as 2026, now gives 2027 as the start date.[1][2] Under the earlier schedule the section was to open in 2029; according to Zdopravy.cz it is not clear whether that date will shift.[2]
Chronology
- — The start of construction on the D55 section between Olomouc and Přerov is being postponed from 2026 to 2027 because of an objection by one of the unsuccessful bidders. → Deník: Olomoucký kraj Zdopravy.cz