In November 2026 the council of the Ústí nad Labem Region selected České dráhy as the operator of five railway lines in the region. The contract is to run from December 2031 to December 2046 and provides for 23 battery electric multiple units. The estimated value of the contract is CZK 19.44 billion excluding VAT at the maximum scope of service.[1][3]
Tender
Six carriers originally applied for the contract, and four of them submitted final bids. The evaluation committee chose the bid of České dráhy, priced at CZK 240.67 excluding VAT per train-kilometre, as the most economically advantageous, and the council approved the choice. According to Ekonomický deník, tender participants may appeal the decision.[1][3] According to regional spokeswoman Magdalena Fraňková, the basic scope of service has an estimated value of about CZK 14.95 billion. The maximum scope allows for up to 25 percent more services.[1]
Lines and start of operation
The contract covers the lines Lovosice – Teplice (U6), Jirkov – Chomutov – Žatec – Louny – Litoměřice – Česká Lípa (U11), Osek město – Most – Louny – Rakovník (U12), Ústí nad Labem – Lovosice – Louny – Žatec (U52) and Ústí nad Labem – Děčín – Česká Lípa – Liberec (L2).[3][4] From December 2031 the units are to run on lines L2, U12 and U52, with 12 sets including two spares. From December 2032 operation is to expand to lines U6 and U11 and the number of units is to rise to 23, four of them spares. After full launch, about 3.53 million train-kilometres a year are expected.[1][3]
Vehicle requirements
Each unit must offer at least 121 seats, air conditioning, Wi-Fi, power sockets and a first class with at least eight seats. It must also carry at least 12 bicycles, two prams and two passengers in wheelchairs. The trains are to combine overhead-line power with batteries having a range of at least 80 kilometres at the end of battery life, and to reach 160 km/h on overhead lines and 120 km/h on battery.[1][4]
Subsidy and other tenders
The region is seeking a subsidy from the TRANSGov programme of up to about CZK 2.85 billion for both stages. The first stage succeeded in the first round of the call, while the second finished first below the funding line.[3] Regional governor Richard Brabec (ANO) described the decision as a step towards modernising rail transport in the region.[4] České dráhy won a similar contract in the Vysočina Region for CZK 13.5 billion, Arriva vlaky won in the Plzeň Region and RegioJet in the Hradec Králové Region.[2]
Chronology
- — The Ústí nad Labem Region council decided that five railway lines in the region will be operated from December 2031 to December 2046 by carrier České dráhy with 23 battery trains, under a contract with an estimated value of CZK 19.44 billion excluding VAT. ČTK / České noviny Novinky.cz
Sources
- ČTK / České noviny — 5 November 2026
- Novinky.cz — 5 November 2026
- Ekonomický deník — 5 November 2026
- Deník: Ústecký kraj — 5 November 2026