Slovenské energetické strojárne (SES) is a company that, according to Ekonomický deník, is a member of the SESMETIC – ZEVO Opatovice consortium. Together with the firms I&C Energo and Metrostav CZ, it forms the consortium.[2]
The Opatovice contract
Elektrárny Opatovice signed a contract with the consortium for the construction of a waste-to-energy facility (ZEVO) in the cadastral area of the municipality of Čeperka in the Pardubice area. The municipality of Čeperka has long opposed the plan, and its residents rejected it in a referendum. [3] The value of the contract is almost 6.6 billion koruna. According to Elektrárny Opatovice, roughly four billion koruna of this amount is to be covered by the Modernisation Fund, which comes under the State Environmental Fund of the Czech Republic. [2] The investor has been promised support of roughly four billion from the Modernisation Fund. [3] The contractor is to provide the design, the supply of technology and the construction itself, and to put the facility into operation.[1] Work is to begin in February 2027, and preliminary acceptance of the facility is planned for March 2030. The facility is to process up to 150,000 tonnes of waste a year.[1][2] The plan obtained a final building permit in July 2026, after the town of Hradec Králové and the municipality of Opatovice nad Labem, among others, had appealed against the first permit. [2] The heat produced is to be supplied through the district heating system, and the plan also envisages electricity generation. For the project, Elektrárny Opatovice have been promised a subsidy of four billion koruna from the Modernisation Fund. [1]
According to ČTK, the same consortium is also building a ZEVO in Komořany near Most.[1] Elektrárny Opatovice obtained the building permit in April 2025, but Hradec Králové, Opatovice nad Labem and other municipalities appealed; it became final in July 2026. [2] According to the source, from 2030 Czechia will end the possibility of landfilling municipal waste that can be used for energy. [2]
The heat produced is to be distributed through the district heating system, and the facility is also to produce electricity. [1]
Chronology
- — Elektrárny Opatovice signed a contract for the construction of a waste incineration plant (ZEVO) in the cadastral area of the municipality of Čeperka in the Pardubice area for almost 6.6 billion koruna, even though local residents had rejected the plan in a referendum. → ČTK / České noviny Novinky.cz
Sources
- ČTK / České noviny — 5 November 2026
- Ekonomický deník — 5 November 2026
- Ekolist.cz — 6 November 2026