Na snímku: Čeperka (ilustrační snímek)
Pictured: Čeperka (illustrative photo)Photo: Petr1888, 2013 · CC BY-SA 3.0 · Wikimedia Commons

The company Elektrárny Opatovice has signed a contract for the construction of a waste-to-energy plant (ZEVO) in the cadastral area of the municipality of Čeperka in the Pardubice region. The contract is worth almost CZK 6.6 billion [1][3]. The construction will be carried out by the SESMETIC – ZEVO Opatovice consortium, formed by the companies Slovenské energetické strojárne, I&C Energo and Metrostav CZ [1].

Project parameters

Once completed, the incineration plant is expected to process 150,000 tonnes of waste a year [1][2]. The heat generated is to be distributed through the district heating network, and the project also envisages electricity production [1]. Elektrárny Opatovice spokeswoman Hana Počtová stated that the contractor will handle the design, supply of technology and construction, and will put the plant into operation [1]. Work is expected to begin in February 2027, with preliminary handover of the facility expected in March 2030 [1][3]. The company has received a pledge of a CZK 4 billion subsidy for the project from the Modernisation Fund [1][3]. The same consortium is also building the ZEVO plant in Komořany near Most [1].

Opposition from Čeperka and the long road to approval

Residents of Opatovice nad Labem rejected the construction of the incineration plant in a referendum in 2006, so the power plant moved the project to another part of the site, which lies within the cadastral area of the municipality of Čeperka [1][3]. Residents of Čeperka subsequently also rejected the project in a referendum [1][2][3]. According to Ekonomický deník, Elektrárny Opatovice also prepared a backup option of moving the incineration plant to the cadastral area of the municipality of Hrobice, but the facility will ultimately be built on the territory of Čeperka [3]. The project received a building permit in April 2025; the City of Hradec Králové, Opatovice nad Labem and other neighbouring municipalities appealed against the decision, and the project obtained a final building permit in July 2026 [3].

Connection to the move away from coal

Elektrárny Opatovice plans to stop using brown coal as fuel entirely by the end of 2030, replacing it with natural gas and the incineration of municipal waste [1][3]. At the end of 2027, the power plant intends to take over the first of three planned combined-cycle gas units, for the gasification of which it received about CZK 3.5 billion from the Modernisation Fund [1][3]. The Opatovice power plant was completed in 1960 [1][3]. It is owned, through its subsidiary EP Energy, by Energetický a průmyslový holding, which is controlled by Daniel Křetínský [1][3]. The power plants supply heat through a network approximately 320 kilometres long to more than 63,000 households in the Hradec Králové – Pardubice – Chrudim agglomeration [1][3].

Chronology

  • — Elektrárny Opatovice signed a contract worth almost CZK 6.6 billion for the construction of a waste incineration plant (ZEVO) in the cadastre of the village of Čeperka in the Pardubice Region, despite local residents having rejected the project in a referendum. ČTK / České noviny Novinky.cz

Sources

  1. ČTK / České noviny — 5 November 2026
  2. Novinky.cz — 5 November 2026
  3. Ekonomický deník — 5 November 2026