The bridge on the regional road between Vřesová and Vintířov carries the road over Chodovský potok and a local road in the area of Stará Chodovská, part of the town of Chodov in the Sokolov district. It is undergoing modernization, the completion of which is being delayed, according to the Krajská správa a údržba silnic Karlovarského kraje (KSÚS), due to construction defects discovered after the work began.[1]
Defects Found
According to KSÚS spokesman Vaněk, it will be necessary to repair the sides of the girders and the joints between them, treat exposed reinforcement, and add protective filling around the prestressing cables.[1]
“We must resolve the newly discovered shortcomings before traffic is restored, even though it means extending the construction. We realise that a longer closure complicates people’s everyday journeys, but the safety of drivers comes first for us. The aim is to open the bridge as soon as possible, but with certainty that it will serve safely in the years to come.”
A subsequent structural recalculation also showed that installing the new bearings will require demolishing and recasting the bearing seats on both bridge abutments over a larger area, along with additional anchoring. The original project documentation did not account for this scope of work, which, according to Vaněk, changes the procedure and extent of the construction so significantly that the contractor cannot meet the originally planned completion date.[1]
Regional Response
Jiří Šlachta, director of KSÚS Karlovy Vary Region, stated: "We must resolve the newly discovered deficiencies before reopening the bridge to traffic, even though this means extending the construction period. We are aware that a longer closure complicates residents' daily commutes, but the safety of drivers remains our top priority. Our goal is to open the bridge as soon as possible, but with the certainty that it will serve safely for years to come."[1]
Šlachta also said that, barring further unforeseen circumstances, road authorities will aim to have the bridge back in operation by early December 2026.[1]
Financing and Traffic
The bridge modernization is being financed by the Karlovy Vary Region, with VIAMONT Servis a. s. as the contractor. The original contract price was approximately CZK 19.7 million including VAT; it is not yet clear by how much this amount will increase due to the additional work, as this will depend on a more precise assessment of its scope.[1]
According to the latest traffic count from 2025, an average of 1,628 motor vehicles pass through the section in both directions daily, including trucks and scheduled buses. According to KSÚS, the bridge serves the daily commuting needs of residents of the surrounding municipalities and is also important for supply and services in this part of the Sokolov district.[1]
Related entries: Karlovy Vary Region, Sokolov, Stará Chodovská
Chronology
- — The reconstruction of the bridge at Stará Chodovská in the Sokolov area will take longer because of defects found later; the Karlovy Vary Region road administration aims to reopen it in early December. iDNES.cz: Karlovy Vary iROZHLAS