NCKV is a company that owns the land in the site of the former brewery in Rybáře in Karlovy Vary. In October 2026 it presented a project for the New Centre district, whose first phase of roughly 73 flats is, according to the plan, to be financed from the company's own funds and bank sources. According to Příkop, the cost of this phase could reach roughly 350 to 400 million koruna.[1] The project was presented by its general manager Miroslav Příkop.[1] According to Příkop, excavation work is to begin in November 2026, construction with a contractor in spring 2027, and the whole realisation of the first buildings is to take about two and a half years.[1]
The development study for the district envisages about two hundred flats in total, which could be followed towards the south by the construction of roughly eighty more.[1]
Chronology
- — The investor NCKV presented in Karlovy Vary a project for the New Centre district in Rybáře on the site of a demolished brewery, whose first phase of 73 flats is planned to begin with excavation work in November. → Karlovarská Drbna