The Krajská správa a údržba silnic Karlovarského kraje has announced that the reconstruction of the bridge near Stará Chodovská in the Sokolov district will be extended because of defects found after work began, and it aims to reopen the bridge at the beginning of December 2026.
The bridge on the regional road between Vřesová and Vintířov crosses the Chodovský potok stream and a local road in Stará Chodovská, which is part of the town of Chodov in the Sokolov district. It is undergoing modernisation, the completion of which, according to the Krajská správa a údržba silnic Karlovarského kraje (KSÚS), is being postponed because of structural defects found after work began.[1]
“We must resolve the newly discovered shortcomings before traffic is restored, even though it means extending the construction. We realise that a longer closure complicates people’s everyday journeys, but the safety of drivers comes first for us. The aim is to open the bridge as soon as possible, but with certainty that it will serve safely in the years to come.”
Defects found
According to KSÚS spokesman Vaněk, it will be necessary to repair the sides of the girders and the joints between them, treat exposed reinforcement and add protective filling around the prestressing cables.[1]
A follow-up structural recalculation further showed that, in order to fit the new bearings, the bearing seats on both abutments of the bridge will have to be demolished and concreted again on a larger scale, and their anchoring supplemented. The original design documentation did not provide for work on this scale, which, according to Vaněk, changes the procedure and scope of the construction to such an extent that the contractor cannot meet the originally planned completion date.[1]
The region's response
The director of KSÚS of the Karlovy Vary Region, Jiří Šlachta, said: "We must resolve the newly found deficiencies before traffic is restored, even if it means extending the construction. We realise that a longer closure complicates people's everyday journeys, but the safety of drivers comes first for us. The aim is to open the bridge as soon as possible, but with the certainty that it will serve safely in the years to come."[1]
Šlachta also said that, unless other unforeseen circumstances arise, the road maintenance workers will aim to have the bridge in operation at the beginning of December 2026.[1]
Funding and traffic
The modernisation of the bridge is funded by the Karlovy Vary Region, and the contractor is VIAMONT Servis a. s. The original price of the contract was approximately CZK 19.7 million including VAT; by how much the sum will rise because of the additional work is not yet clear and will depend on specifying its scope.[1]
According to the latest traffic census, from 2025, an average of 1,628 motor vehicles a day pass through the section in both directions, including lorries and scheduled buses. According to KSÚS, the bridge serves the everyday journeys of residents of the surrounding villages and is also important for supplies and services in this part of the Sokolov district.[1]
Related entries: Karlovy Vary Region, Sokolov, Stará Chodovská
Chronology
- — The reconstruction of the bridge at Stará Chodovská in the Sokolov area will take longer because of defects found later; the Karlovy Vary Region road administration aims to reopen it in early December. iDNES.cz: Karlovy Vary iROZHLAS