David Fiala heads the Brno branch of the state organisation Ředitelství silnic a dálnic (ŘSD).[1][2]

At a briefing on 19 November 2026 he announced that the Pisárecký tunel in Brno, closed for the renovation of its technology, would remain shut possibly up to nine days longer than planned. He said that the company Eltodo had not completed the work by the deadline set in the contract and that ŘSD learned of its request to extend the closure from the regional office only that morning. He added that, if the contractor's fault is proven, it will pay one million crowns for each extra day, and that the tunnel will open sooner if that is safe.[1][2] Fiala said that ŘSD had originally counted on opening the tunnel by the original deadline under extraordinary safety measures. [3] According to him, ŘSD has no agreement with the company on who was to install the electricity meters, and ŘSD itself was to have them installed so that the work could continue. [1] According to Fiala, on 19 November 2026 the light signs, SOS call points and fire-protection systems had not been installed in the tunnel. [1] At a meeting at the regional office on 20 November 2026, Eltodo said it would finish the work by Sunday 29 November. [3]

The mayor of Brno, Jakub Hruška (KDU-ČSL), said that the city and its companies would quantify the costs caused by the extension of the closure, in particular for the transport company because of reinforcement services. [3]

The Pisárecký tunel has been in operation since 1998, and ŘSD will pay CZK 212 million for the current renewal of its technology. [4]

Hruška said that the city wants to demand compensation for the costs of reinforcing public transport and other extraordinary measures, and is prepared to enforce it in court if the parties do not agree. [3]

Rostislav Snovický, head of the regional transport department, confirmed that the closure will be illegal for the duration of the extension, because in practice its approval takes at least five days; in his view the contractor and the investor bear responsibility, and the sanction will be dealt with by Brno City Hall. [3]

Fiala also said that ŘSD at that time had no agreement with the company on who was to install the electricity meters, and that ŘSD wanted to have them installed the following day so that the work could continue. [1]

Fiala said that the road workers had assumed it might be possible to put the tunnel into operation by the original deadline under extraordinary safety measures. [3]

At the meeting at the regional office on 20 November 2026, according to Fiala and the Brno mayor Jakub Hruška (KDU-ČSL), the company said it would finish the work by Sunday 29 November. [3]

Sources

  1. Práce v Pisáreckých tunelech se podle ŘSD protáhnou nejméně o devět dnů · ČTK / České noviny · 19 November 2026
  2. Pisárecké tunely se v sobotu neotevřou. Zhotovitel nestíhá, uzavírka se protáhne · Zdopravy.cz · 19 November 2026
  3. Pozdvižení v Brně. Oprava Pisáreckých tunelů se protáhne, město chce náhradu nákladů · Echo24 · 20 November 2026
  4. Dopravní peklo nekončí. Pisárecké tunely zůstanou zavřené déle, firma se zpozdila · Brněnská Drbna · 20 November 2026