Image from the publication Novinky.cz
Image from the publication Novinky.cz, 29 October 2026

The Korean company KHNP told the Czech News Agency on 29 October 2026 that it had formally terminated negotiations on a construction contract for the project of new nuclear units at Dukovany with a consortium of the Korean firms Daewoo Engineering & Construction and Doosan Enerbility. According to KHNP, the reason is differing positions on key contractual terms. The company is starting the process of terminating the existing cooperation agreement with the consortium and is preparing a new tender for a construction contractor. At the same time it wants to ensure continuity of key parts of the project during the transition period and carry out some steps directly.[1][2]

According to the website Novinky.cz, which draws on information from the Korean website BusinessKorea and on confirmation from KHNP, neither the working-level talks, nor the meeting of the coordination committee, nor the discussions between the firms' leadership led to an agreement. According to Novinky, the dispute concerned mainly the calculation of construction costs and the allocation of the risk of their possible increase. According to the same source, the consortium argues that as a construction contractor it cannot bear all additional costs caused by changes to the technical design without an adjustment of the price. According to Novinky, both firms rejected that the talks had ended in failure and said that they had wanted to continue until at least the end of the year.[2]

According to a KHNP representative cited by Novinky, a new partner for the construction work is to be selected by July 2027. Preparatory work on the site is to begin in January 2028, the main construction work in November 2029, and the first reactor is to enter trial operation in 2036.[2] KHNP signed the main contract with the investor, the company Elektrárna Dukovany II, in June 2025. Its value is CZK 407 billion excluding VAT.[2]

Minister of Industry and Trade Karel Havlíček (ANO) told the Czech News Agency that, according to the Korean minister's assurance, neither the construction nor its schedule is at risk. According to Havlíček, KHNP is prepared to negotiate with other construction contractors as well, and there is no shortage of interested large firms. He added that Czechia leaves the matter to the Korean side, which is the guarantor of the overall delivery.[1]

The end of the negotiations does not affect the other contracts. Doosan Enerbility has separate contracts with KHNP for the supply of the nuclear steam supply system and the turbogenerator, with the turbine and turbine hall equipment to be supplied by its subsidiary Doosan Škoda Power from Plzeň. KHNP has also concluded a contract for design and engineering work with Kepco Engineering & Construction. Negotiations on nuclear fuel supplies with Kepco Nuclear Fuel and on commissioning and maintenance of the plant with Kepco KPS are continuing, and their conclusion is expected next year.[1][2]

The shares of both firms fell in response to the news. According to Novinky, on the morning of 29 October Daewoo E&C shares fell by more than 21 percent and Doosan Enerbility shares by more than 11 percent.[2]

Chronology

  • — South Korean company KHNP ended without agreement its negotiations with a consortium of Daewoo Engineering & Construction and Doosan Enerbility on a contract for construction works on the project of new nuclear units in Dukovany. Novinky.cz ČTK / České noviny

Sources

  1. KHNP ukončila bez dohody jednání o smlouvě na stavební práce v Dukovanech · ČTK / České noviny · 29 October 2026
  2. Dostavba Dukovan se komplikuje kvůli sporu korejských firem · Novinky.cz · 29 October 2026