After a six-week refurbishment of its technology, the Pisárecký tunel in Brno was to reopen on Saturday 21 November 2026. David Fiala, director of the Brno branch of the Ředitelství silnic a dálnic (ŘSD), said at a briefing on 19 November that it could remain closed for up to nine days longer. According to him, the contractor, the company Eltodo, did not manage to complete the work by the contractual deadline.[1][2]

Dispute over the causes

Fiala said that in the morning the ŘSD learned that the contractor had asked the regional office to extend the closure by nine days without informing the client. According to him, the tunnel has no light signs, SOS call boxes or fire-protection systems installed, although all systems were supposed to be ready for individual tests on 12 November. Eltodo told the Czech News Agency that the work is in its final phase. Petr Kovář, executive director of the company's transport division, said that tests of the newly installed equipment have not yet begun and will begin after the electricity meters are delivered and installed and the tunnel is connected to the distribution grid, which the ŘSD is to arrange. Fiala said that the parties disagree on who was supposed to install the meters and that the ŘSD will nevertheless provide them on Friday 20 November.[1][2]

If the contractor is found at fault, it will, according to Fiala, pay a contractual penalty of one million koruna for each additional day. If the tunnel can be opened earlier, the ŘSD will do so, according to him, even if not all systems are in operation, because safety is decisive. A coordination meeting was called for Friday at the regional office with the police, the transport company, the city and representatives of the firm.[1]

Impact on traffic

The spokeswoman of the transport company, Hana Tomaštíková, described the extension as a complication for drivers and for the company, which had adapted to the planned duration of the closure. Measures linked to the closure remain in force: reinforcement services on line 37 between Kohoutovice and the Nemocnice Bohunice terminal, tram line P6 from the Mendlovo náměstí terminal, and the diversion route of express line E56.[1]

Sources

  1. Práce v Pisáreckých tunelech se podle ŘSD protáhnou nejméně o devět dnů · ČTK / České noviny · 19 November 2026
  2. Pisárecké tunely se v sobotu neotevřou. Zhotovitel nestíhá, uzavírka se protáhne · Zdopravy.cz · 19 November 2026