The Pisárecký tunel in Brno, which is key to traffic in the city, was due to reopen on Saturday 21 November 2026 after a six-week refurbishment of its technology. David Fiala, who heads the Brno branch of Ředitelství silnic a dálnic (ŘSD), said at a briefing on 19 November that it may stay closed for up to nine days longer because the company Eltodo did not finish the work by the deadline set in the contract.[1][2]
Fiala said the ŘSD learned that morning that the contractor had asked the regional authority to extend the closure without the client's knowledge. A coordination meeting of all those involved, including the police, the transport company and the city, was called at the regional authority for Friday 20 November; Eltodo was invited as well.[1][2]
Eltodo told the Czech News Agency that the work is nearing completion. Petr Kovář, executive director of the company's transport division, said that tests of the new equipment have not started yet; they can begin once the ŘSD provides electricity meters and the connection of the tunnel to the distribution network, and the company expects nine days for the safe connection and the tests. According to Fiala, the ŘSD and the company disagree over who was supposed to install the meters, but on Friday 20 November the ŘSD will arrange the installation so that the work can continue.[1]
According to Fiala there are so far no light signs, SOS call points or fire systems in the tunnel, although the systems were due to be ready for individual tests on 12 November and for tests as a whole on 16 November. If the supplier is found at fault, it will pay one million koruna for every extra day. Fiala added that if the tunnel can be opened sooner than in nine days, it will happen even with the systems only partly operating, and that safety will be the key consideration.[1]
The Dopravní podnik města Brna is keeping the measures linked to the closure: the reinforced line 37 between Kohoutovice and the Nemocnice Bohunice terminal, the tram line P6 from the terminal at Mendlovo náměstí, and the diversion of express line E56. The company's spokeswoman Hana Tomaštíková described the situation as a complication for the agreed driver shifts and for informing passengers.[1]
Chronology
- — The Pisárecký tunel in Brno will stay closed for up to nine days longer than planned after its equipment overhaul, said David Fiala, head of the Brno branch of the Ředitelství silnic a dálnic. ČTK / České noviny Zdopravy.cz