Povodí Odry has completed the last section of flood protection for Bohumín in the Pudlov district: almost three kilometres of embankments costing more than CZK 400 million.
The state enterprise Povodí Odry has completed the last stage of flood protection for Bohumín in its Pudlov district. The new embankment is 2,829 metres long and, depending on the terrain, between 1.5 and four metres high. The project also includes a 190-metre flood wall, new bridges, access roads and culverts, as well as relocations of water mains, gas pipelines and power lines.[2]
Construction began in the autumn of 2022 and was divided into three stages. The last stage cost more than CZK 400 million, of which almost CZK 290 million was provided by the Ministry of Agriculture and the remaining CZK 110 million was paid by Povodí Odry. The total cost of the flood protection works in the Bohumín area, including project preparation, reached about CZK 570 million.[2]
The embankment is meant to protect the town against a 100-year flood. It also includes underground sealing elements and measures against seepage beneath the railway embankment.[1] The project was preceded by the settlement of property rights, which took ten years. The town and the Moravian-Silesian Region each contributed CZK 4 million to the purchase of land, said Povodí Odry director general Miroslav Janoviak.[1][2]
Bohumín was hit by floods in 1997, 2010 and 2024. According to mayor Lumír Macura, the damage in the town from the flood in September 2024 reached CZK 1.4 billion, the water affected more than a thousand households, and because of a flooded distribution substation in Pudlov, part of the town was without electricity for several days. Macura said the town had waited a quarter of a century for complete protection. Next year Povodí Odry intends to ask the regional water authority to update the flood zone of the Bohumín area.[1][2]