Image from publication Deník: České Budějovice / Jižní Čechy
Image from publication Deník: České Budějovice / Jižní Čechy, 17. 11. 2026

Technicians at the Temelín Nuclear Power Station began in November 2026 to move four casks of spent nuclear fuel to the storage facility there. After further checks, the casks are to fill storage positions 79 to 82. The first casks have already been moved to the facility, and the remaining ones are to be stored in the coming days.[1]

The total capacity of the facility is 152 positions and, according to the source, about half of it is currently in use.[1] The storage takes place under the supervision of inspectors of the International Atomic Energy Agency.[1]

Sources

  1. Deník: České Budějovice / Jižní Čechy — 17 November 2026