According to the explanatory report of an approved document of the City of Prague, the two bridges over Sulická Street in Krč will not be reconstructed. The existing structures are to be removed and replaced by new three-span bridges. The reasons are the poor structural condition and the need for coordination with the construction of metro line D.[1][2]
The condition of both bridges was rated grade VII, which means a need for a comprehensive solution. Surveys found defects related to water leakage, degradation of concrete, corrosion of reinforcement and an increased chloride content in some parts of the structures. The section is heavily used; according to City Hall data from 2025, about 125,000 vehicles pass through it per day, roughly a tenth of which is heavy traffic.[1][2]
The city originally planned reconstruction. The October 2024 brief was based on the condition known at the time and assumed rehabilitation of the load-bearing structure and substructure and replacement of the bridge joints and related equipment. The city provisionally estimated the cost of the new construction at 487.4 million crowns including VAT. The amount covers project preparation, surveys, the design for the contractor and the construction itself.[1][2]