The ČEZ Group was completing a new rooftop photovoltaic power plant on 25 November 2026 at the Dlouhé stráně pumped-storage power plant. It will supplement the small hydropower plant at the outflow from the lower reservoir, and the two sources are together to supply the complex's operations with electricity from renewable sources.[1]
The sources are to cover a large part of the so-called common own consumption, that is, the consumption of all facilities other than the power plant's main technological equipment. This includes, for example, buildings, lighting, heating, security and control technology. The instantaneous value of this consumption is about 350 kW, which is close to the combined output of the small hydropower plant and the new photovoltaic plant. According to ČEZ Group spokesman Vladislav Sobol, the sources do not reach their maximum at the same time, so over the year they will complement each other and increase the complex's energy self-sufficiency.[1]
The head of Dlouhé stráně, Ludvík Štrobl, said that the photovoltaic plant will complement the output of the small hydropower plant: in periods of peak solar production, flows at the outflow from the lower reservoir tend to be lower. The plant is being built by the company MARTIA, which is part of the ČEZ Group.[1]
According to the director of ČEZ's hydropower plants, Róbert Heczko, the project follows on from regular investment in the modernisation of Dlouhé stráně, which exceeded 800 million crowns in 2024 to 2025 and continues in 2026.[1]
Chronology
- — ČEZ Group is completing a photovoltaic power plant at the Dlouhé stráně pumped-storage power station, which, together with a small hydroelectric plant at the outflow of the lower reservoir, is to cover part of the site's own electricity consumption. Novinky.cz