Pictured: Rožnov pod Radhoštěm (illustrative photo)
Pictured: Rožnov pod Radhoštěm (illustrative photo)Photo: Tedmek, 2008 · public domain · Wikimedia Commons

The American semiconductor manufacturer onsemi (ON Semiconductor) has announced the cancellation of plans to expand production at its plant in Rožnov pod Radhoštěm in the Vsetín District[1]. The company had estimated the planned investment at two billion dollars, or roughly 43.5 billion Czech koruna at the then-current exchange rate[1][2].

Company's Announcement

The company announced the cancellation of its plans in a press release[1][2]. It cited developments in the silicon carbide market and a change in the project's economics as the reason[1][4]. According to the company, the decision does not affect current production at the plant[2][4]. "The decision relates specifically to developments in the global silicon carbide market and in no way reflects an assessment of the investment environment in the Czech Republic, which remains an important part of onsemi's long-term manufacturing and growth strategy," the company stated[1][3][4].

Minister of Industry and Trade Karel Havlíček (ANO) said in the company's statement that production in Rožnov pod Radhoštěm and onsemi's investment in Czechia would continue[1][2][3].

Previous Plans and Development of the Investment

The company announced plans to expand the Rožnov plant in 2024, intending to build a complete production chain for silicon carbide, used as a semiconductor material[1][4]. Onsemi's main production plant in Czechia, along with a development center, is located in Rožnov pod Radhoštěm, and the company also operates another branch in Brno[1][4]. In May 2026, the company laid off about 200 of the roughly 1,700 employees at the Rožnov plant[3].

“The decision relates specifically to developments in the global silicon carbide market and in no way reflects an assessment of the investment environment in the Czech Republic, which remains an important part of onsemi's long-term manufacturing and growth strategy”

According to the company[2]

The Town's Reaction

The mayor of Rožnov pod Radhoštěm, Jan Kučera (Independent Rožnováci), described the cancellation of the plans as bad news[3]. According to his statement to the Czech News Agency, the production expansion had been an opportunity for the town, the region and the country, and it is a shame it did not happen[4].

According to Kučera, the town had prepared a plan called MiliJarda for the potential investment, divided into three stages[3][4]. "As a town, we were cautious, so we prepared the MiliJarda plan... and we divided it into three stages. We carried out the first stage using projects that the town needed anyway and that were also meant to support the investment," the mayor said[4]. The other two stages were only to be launched if the investment actually went ahead[4]. According to Kučera, the cancellation of the plans has no negative impact on the town's budget, since no special expenses had been incurred for the investment[3][4]. He added that onsemi remains firmly rooted in Rožnov pod Radhoštěm for the long term and that existing chip production continues to operate[3][4].

History of the Plant

The company ON Semiconductor Czech Republic continues the production tradition of the former state-owned enterprise TESLA and was established in 2003 through the merger of the companies TESLA SEZAM and TEROSIL[3]. It is owned by the American technology group onsemi (ON Semiconductor)[3]. The plant focuses on the production of silicon and silicon carbide wafers, semiconductor chips, operational amplifiers, comparators, regulators, switching power supplies, voltage controllers and automotive electronics[3].

Chronology

  • — American semiconductor manufacturer onsemi cancelled plans to expand production at its plant in Rožnov pod Radhoštěm worth about CZK 43.5 billion. ČTK / České noviny ČT24

Sources

  1. ČTK / České noviny — 6 November 2026
  2. ČT24 — 6 November 2026
  3. Novinky.cz — 6 November 2026
  4. Seznam Zprávy — 6 November 2026